CEO of APPM, "Vladimir Krupchak donated to the monastery not just a blagovest bell – it is the voice of the Siysky religious house soul"OMET will supply a table napkins production line to Arkhbum Tissue GroupArkhangelsk PPM became a prime sponsor of Earth Overshoot Day 2020Arkhbum-Pack and the Government of the Kaluga Region signed an Agreement of Intent on the implementation of an investment project for the construction of a plant for the production of consumer packageAt the end of 2020, the Ulyanovsk branch of Arkhbum will start commissioning of the corrugatorCorrection: Since October 21, 2019, the Pulp Production Plant of Arkhangelsk PPM has improved the ECF pulp bleaching technologyCEO of APPM, "Vladimir Krupchak donated to the monastery not just a blagovest bell – it is the voice of the Siysky religious house soul"OMET will supply a table napkins production line to Arkhbum Tissue GroupArkhangelsk PPM became a prime sponsor of Earth Overshoot Day 2020Arkhbum-Pack and the Government of the Kaluga Region signed an Agreement of Intent on the implementation of an investment project for the construction of a plant for the production of consumer packageAt the end of 2020, the Ulyanovsk branch of Arkhbum will start commissioning of the corrugatorCorrection: Since October 21, 2019, the Pulp Production Plant of Arkhangelsk PPM has improved the ECF pulp bleaching technologyCEO of APPM, "Vladimir Krupchak donated to the monastery not just a blagovest bell – it is the voice of the Siysky religious house soul"OMET will supply a table napkins production line to Arkhbum Tissue GroupArkhangelsk PPM became a prime sponsor of Earth Overshoot Day 2020Arkhbum-Pack and the Government of the Kaluga Region signed an Agreement of Intent on the implementation of an investment project for the construction of a plant for the production of consumer packageAt the end of 2020, the Ulyanovsk branch of Arkhbum will start commissioning of the corrugatorCorrection: Since October 21, 2019, the Pulp Production Plant of Arkhangelsk PPM has improved the ECF pulp bleaching technology

Arkhbum JSC has started the active phase of the investment project for the construction of the Ulyanovsk site

23 jun 2020

After removing the restrictions related to COVID-19, Arkhbum JSC started the implementation of the first stage of the investment project in the Volga Federal District - the construction of a new corrugated board plant in Ulyanovsk.

Currently, a set of works is underway to prepare the facility for comprehensive reconstruction, including modernization of the administrative building, installation of on-site engineering networks and communications (gas, electricity, water, sewage), construction of roads and related infrastructure facilities.

In addition to the existing BHS corrugator, two BOBST conversion lines will be installed in the Ulyanovsk branch of Arkhbum. The installation will begin at the end of this year.

Due to the force majeure situation associated with the pandemic, the company expects to launch a new corrugated plant in March 2021.

In 2021 — 2023, Arkhbum JSC will begin the implementation of the second stage of the reconstruction of the Ulyanovsk site: it is planned to install four more processing lines, to increase storage facilities, etc.

The cost of the company's program is estimated at 2.5 billion rubles.

As previously reported, the capacity of the new production in Ulyanovsk for the production of corrugated packaging and corrugated cardboard is 16 million m² per month (annual potential is 192 million m²).

Market potential of the Volga Federal District is estimated at almost 1.4 billion m² per year.

The plant will produce products similar to those produced at the sites of Arkhbum JSC in Podolsk, Istra-1, Istra-2 and Voronezh: 3-and 5-layer corrugated products - 4-valve corrugated boxes, rotary and flat die cut boxes.

Reference

Arkhbum JSC is a daughter company of Arkhangelsk PPM JSC (sole shareholder – Pulp Mill Holding).

Main business area – corrugated packaging.